2013

Period Covered: From 2013 and 2014
cmed.pdf  
ITEM # NAME OF PROJECT REMARKS
01 Dagami - Kiling Pipeline Project, 250mmØ (10"Ø) uPVC Provincial Funded
02 Baras - Salvacion Pipeline Project, 160mmØ (6"Ø) uPVC Provincial Funded
03 Pastrana -Sta. Fe Pipeline Project, 110mmØ (4"Ø) uPVC Provincial Funded
04 Palo - Arado - Libertad Pipeline Project, 110mmØ (4"Ø) uPVC Provincial Funded
05 Palo - Tacuranga - San Antonio Pipeline Project, 110mmØ (4"Ø) uPVC Provincial Funded
06 Maca - alang - Patoc - Calipayan Pipeline Project, 160mmØ (6"Ø) uPVC, 110mmØ (4"Ø) uPVC & 63mmØ (2"Ø) PE Provincial Funded
07 Capulhan - Canlingga Pipeline Project, 63mmØ (2"Ø) PE Provincial Funded
08 Cansamada - Kiling - Malaguicay - Maribi - Pago Pipeline Project, 63mmØ (2"Ø) PE Provincial Funded
09 Salvacion - San Joaquin - Mohon - Cabuynan Pipeline Project, 63mmØ (2"Ø) PE Provincial Funded
10 Guindapunan - Calsadahay - Macalpiay - Malitbogay - Lourdes Pipeline Project, 63mmØ (2"Ø) PE Provincial Funded
11 Gacao - San Isidro - Anhaway - Teraza - Castilla - Cabaohan - Jones Pipeline Project, 63mmØ (2"Ø) PE Provincial Funded
12 Dagami - Kiling Pipeline Project, 250mmØ (10"Ø) uPVC Provincial Funded
13 Salvador - Binongto-an Pipeline Project, 63mmØ (2"Ø) PE CALAHI - CIDSS Funded
14 Guingauan Pipeline Project, 63mmØ (2"Ø) PE CALAHI - CIDSS Funded
15 Mercadohay Pipeline Project, 63mmØ (2"Ø) PE CALAHI - CIDSS Funded
16 Dagami - San Benito - Abaca Pipeline Project, 110mmØ (4"Ø) uPVC DILG, LGU
17 Provincial Hospital Pipeline Project, 110mmØ (4"Ø) uPVC/PE Provincial Funded, LMWD
18 APAC Pipeline Project, 110mmØ (4"Ø) PE Provincial Funded, LMWD
19 Rainbow Village Pipeline Project, 90mmØ (3"Ø) PE LMWD
20 Basilan - Delgado Subdivision Pipeline Project, 63mmØ (2"Ø) PE LMWD
21 Yougfield Pipeline Replacement Project, 110mmØ (4"Ø) PE - 90mmØ (3"Ø) LMWD
New Water Service Connection installation data
2014
NWSC Application Size of Connection: ½"ø Size of Connection: ¾"ø Size of Connection: 1"ø Size of Connection: 2"ø Size of Connection: 4"ø
No. of approved NWSC application received 1271
No. of installed NWSC 1303 2 5 6 -
Transfer of Tapping and Transfer of Connection
 2014
Request Size of Connection: ½"ø Size of Connection: ¾"ø Size of Connection: 1"ø Size of Connection: 2"ø Size of Connection: 4"ø Total
No. of request for transfer of tapping received 91 91
No. of request implemented 88 88
Hydro-testing and Interconnection data
 2013-2014
Activty/ies No. of Request
Received: 2013
No. of Request
Received: 2014
No. of Request
Implemented: 2013
No. of Request
Implemented: 2014
Pipeline Hydrostatic Test 8 7 8 7
Pipeline Interconnection 8 7 8 7
Cutting and Breaking and Restoration Works
 2014
Activty/ies National Road Provincial Road City/Municipal Road Barangay Road Total
No. of request for Cutting and Breaking of Concrete Pavement received
No. of Cutting and Breaking of Concrete Pavement conducted 65 7 53 76 201
No. of request for Restoration of Broken Pavement received
No. of Restoration of Broken Pavement conducted
Total 65 7 53 76 201
2014
Item No. NAME OF PROJECT REMARKS
01 San Joaquin - Cabarasan Guti Pipeline Project, 63mmØ (2"Ø) PE DILG,LGU
02 Caloogan - San Jose Pipeline Project, 90mmØ (3"Ø) PE LMWD
03 Sitio Ugsad Pipeline Project, 63mmØ (2"Ø) PE LMWD
~Nothing follows~